Reliability and maintenanceRM-001
Holcim Slovensko · Rohoznik cement plant · 2003-2005
Supplier reports bearing replacement interval on main-kiln fans increased to at least 30 months from less than one year.
Reliability and maintenanceRM-002
Tanga Cement Company · Simba Cement, Tanga · 2004-2010
Supplier reports rotary-kiln availability rose from below 83% in 2004 to above 96% in 2010.
Reliability and maintenanceRM-003
Ceskomoravsky Cement · Radotin cement plant · reported 2021
Plant and supplier report earlier detection, less damage exposure, plannable repairs, and a long-term support contract; no quantified availability delta.
Energy and environmental performanceEE-001
CalPortland Company · Oro Grande Cement Plant · 2022
EPA award profile reports 18% energy-efficiency improvement for the project.
Energy and environmental performanceEE-002
CalPortland Company · Mojave Cement Plant · 2022
EPA award profile reports 40-50% fan-efficiency improvement.